Mailbox Relocation Committee Report

SCHEDULED MOVE DATE MARCH 1 - The construction of the facility is complete, and the driveway, handicap access should be completed by February 25.  The postal service has placed a work order to move the boxes on March 1; the exact method of handling has not been divulged, so every one just be patient with this final step.  The work remaining at the facility will be some clean-up, fence around the one acre which is being retained, and a little landscape work around the area. Initially the number of Parcel Boxes will not change, unless the 4.12 acres sells within the near future.  As Chairperson for the Relocation, thanks to everyone for their comments and I certainly hope everyone is as pleased with the outcome. Special Thanks to all of the Committee Members.